OMG! I Actually Worked On The Master Bathroom

Last fall, I threatened that I would have the master bathroom completed by the end of the winter. Here it is spring and I did almost nothing to the bathroom. I have a variety of excuses that I wont go into now, however I did finally make some actual progress on it this weekend.

Before I can do anything I need to install the pocket door. Before I install the pocket door I need to relocate the wiring that exists on the wall where the door goes.

Original wiring location

The wiring consists of power in, a wire to the lights controlled by a switch and a power out to a outlet. The good news is the wiring was easy to move to the next wall, it was loose in the attic and there was plenty of room to move it. I thought I would leave the outlet unpowered for now, until I figured out how I was going to rewire everything, apparently the wire to the outlet is also hooked up to the living room.

Temporary wiring location

Now I have a problem that I need to wire that outlet back up, so i have Romex running along the other side of the bathroom along up to the switch. It looks pretty messy and dangerous in the pictures, I know. Trust me it’s safe and temporary.

I need to decide how to wire up a exhaust fan, will it go near the light switch or near the toilet? I also need to figure out if I’m going to use a fancy digital shower control. If so It will use the power from the outlet then I can wire it up properly.

Finally I can install the pocket door. I have the studs marked to cut down, but I’m waiting for some friends to come by and verify my measurements before I screw it all up. I will save the pocket door install for another post.

Kitchen Stage One Complete

Stage 1 completeIt’s been a few months since I moved in and started working on the kitchen remodel so I’m glad to report that Stage 1 is complete. Stage 1 is what you see here, with half of the upper cabinets installed including the appliances. Every bit of it built by me. Stage 2 will complete the kitchen with the rest of the cabinets, paint and tiling.

When I first made the offer on the house I wasn’t initially planning to remodel the kitchen. But after spending a few hours in it, it was clear that I was not going to be happy with the wear and tear that had been put on it for 20+ years. I used Home Depot’s design service to do the design, which turned out to be a good deal. It’s costs $100 for them to come out and do the measurements and plug everything into the computer. They give $100 off materials if you buy from them.

When choosing the materials for the cabinets I looked at both the lowest cost and highest cost cabinets. I’m pretty disappointed at the amount of particle board used in the construction of both version. The lowest cost is totally made of particle board except for the doors and are complete do-it-yourself. Where as the more expensive ones are about 50% particle board and are installed by someone else. I went with Mills Pride cabinets that Home Depot keeps on stock because of their much lower costs, significant in some cases. Despite the fact that they are made of particle board they are of pretty good quality and very easy to assemble. Well worth it for the money I saved. I would say it cost around $1000 for this section of cabinets (the maple doors were as much as the cost of the cabinet boxes, that’s the real expense).

Stage 2 will involve taking down the wall on the right and putting in a cabinets along the bottom (this is where the refrigerator originally was). This will open it up to the living room more. I’ve never pulled down a wall before (just as I never did any of this kitchen work before). I will also probably pull out the original tile back spash and put different tile up. I will finish it up with paint, trim and what ever else will be needed. I figure it will cost about $2000 to finish it up (doing it all myself of course) but don’t know when I will start it. In the mean time check out my Flickr photo set showing the stages of the remodel.